2017 Sewer Open Trench Projects

Each year, as part of an ongoing Sewer Infrastructure Rehabilitation Program, the City of Coeur d’Alene Wastewater Utility Department undertakes several sanitary sewer projects to rehabilitate or replace the main sewer pipes.  These projects are needed to improve the system’s reliability, functionality and to extend the system’s useful life.  

This year, contractors will be replacing approximately 2,500 linear feet of sewer mains including lateral reinstatement, surface repair and other associated work at the following four different locations:

  • GARDEN AVENUE BETWEEN MILITARY & PARK DRIVE
  • ALLEY BETWEEN NORTH A & B STREETS AND SHORT & WALNUT AVENUE
  • HASTINGS AVENUE BETWEEN 16TH & 19TH STREET
  • PINES AVENUE BETWEEN TUBBS HILL & 8TH STREET

Contacts:

Project Manager:  Mike Becker, City of Coeur d’Alene, (208) 769-2268, mbecker@cdaid.org

Project Engineer:  Pete Stayton, P.E., JUB Engineers (208) 762-8787, pstayton@jub.com  

News & Information:

Advertisement: January 23 & 30, CDA Press

Project Plans: Linked Here (Note: Large file. Right-click and choose "Save Us" to download)

Pre-bid Conference: 10:30 a.m., January 31, 2017, Wastewater Utility, 765 W. Hubbard Ave.

Bid Opening: 2 p.m., February 7, 2017, City Hall, 710 E Mullan Ave.

Bid Breakdown: 

Bidder

Schedule A,B,C          Base Bid

Schedule D Additive Alternative

Total Bid

Big Sky Development

 $         323,564.35

 $         115,092.44

 $         438,656.79

T. LaRiviere Equipment, Inc.

 $         394,779.70

 $         172,508.00

 $         567,287.70

S & L Underground

 $         438,699.00

 $         186,205.00

 $         624,904.00

Engineer's Estimate

 $450,000 to $500,000 


Contractor Awarded Project: 
Big Sky Development

Preconstruction Meeting: 10 a.m., March 13, 2017, Wastewater Dept., 765 Hubbard Ave.

Open House Meeting: 6:30 p.m., March 15, Boys & Girls Club, 925 15th Street, CDA

6:30 p.m., March 16, Wastewater Dept., 765 Hubbard Ave.

Start-up Date: April 1, 2017 Actual Start-up Date: Pending

Substantial Completion Date:  June 1, 2017 Actual Completion Date: Pending

Project Update:  3/03/17 Big Sky Development returned signed contract to City.  Contractor is also working on Product Submittals.  City is coordinating Preconstruction Meeting, Open House Meetings to get the public’s feedback and working with North Idaho College (NIC) to minimize road closures and detour routes within Fort Grounds Area.