Ash St. Sewer & Water Construction work Scheduled

Posted: 5/11/2020 9:05:34 AM
The City of Coeur d'Alene has scheduled a City sewer and water project in your area. The work will involve excavation of manholes, installation of new manholes and pipe, water service re-routing and road rehabilitation. Construction is scheuled to start on May 11th and be concluded around the 29th of May. Detour routes will be set up for any road or intersection closures. Access may be somewhat limited at times and the Contractor on-site will try to accommodate residents needs.

LOCATION: 
Ash Street between 14th and Dollar St and the Alley between 14th and Dollar.
DATES: 5/11/2020 - 5/29/2020

Here is how you may be affected:
1. Homeowners on Ash between 14th and Dollar may have your driveways blocked on the date(s) listed above and need to find parking elsewhere.
2. Homeowners on the North half of the Alley between Dollar and 14th will have their garbage service disrupted and need to place their cans at the North end of the Alley.
3. This work will occur during daytime hours, involving the operation of motorized equipment near your home or place of business.
4. Dates may fluctuate in duration.

Thank you for your patience. If you have any questions, please contact one of the contacts below:
City's Representative: Jessica Waller, J-U-B Engineers, 208-762-8787
City of Coeur d'Alene, Wastewater Utility: Larry Parsons, Project Manager, 208-769-2268 (office)
Contractor: Steve Thurston, Project Manager, 208-755-9832