2017 Street Overlay & Chip Seal
In an ongoing commitment to provide safe and drivable city streets, the City of Coeur d' Alene annually performs this maintenance and rehabilitation project.
The 2017 overlay includes:
- Front Avenue between 8th and 21st streets, and 9th, 10th, 11th, 12th, 16th
- Between Sherman & Mullan avenues: 9th, 10th, 11th, 12th, 16th, 17th, 18th, 19th, 21st streets
- Between Front and Mullan avenues: 13th and 14th streets
- Between Front and Sherman avenues: 19th street
- Hanley Avenue between Ramsey Road and Highway 95
- Dalton Avenue between N. Stafford Road and N. Pleasant Way
The 2017 chipseal program includes:
- Government Way between Harrison Avenue and Interstate 90
- Best Hill Meadows Subdivision
- Foothills Subdivision
The City of Coeur d Alene has identified and prioritized these areas utilizing pavement rating software, coordination with utilities and City departments, and overall budget resources available.<
Project is the planning stage; we are estimating advertisement for bids in early March 2017
Substantial Completion: Fall 2017
Contacts
Tim Martin, Streets & Engineering Superintendent, email:[email protected]
Kim Harrington, Assistant Project Manager, 208-769-2214 or [email protected]
News & Information
Chipseal Timeline: Begins July 11 and runs for approximately two weeks.
Overlay Timeline: Initial grinding begins July 17 on Front Avenue. Overall length of work, including final paving is to be determined.